Structural refurbishment of the main stand at the FWD-IP Community Stadium. Completed in five days, including disassembling and reassembling.

The Scope of Works
Working ahead of a weekend fixture, our team stripped out the entire stand at Cambridge City FC's stadium, removing each of the original steel support legs one at a time. New, thicker steel legs were supplied to site and installed by our team, who rebuilt the stand, fitted new cladding throughout, and left the ground fully match-ready. The steelwork itself was supplied ready to install — our scope was the on-site structural installation, not fabrication.
5
Days Start to Finish
Complete strip-down, new steelwork installation, and re-cladding, delivered in five days ahead of a weekend fixture.
Match Ready
Deadline Met
Ground fully reassembled and match-ready in time for the weekend fixture.
Scope
Stand Strip & Rebuild
Every steel support leg removed one at a time and replaced with new, thicker steelwork supplied to site.
Before & After
The stand before work began, and the completed rebuild ready for the weekend fixture.